WASTE-TO-ENERGY PLANT BREMERHAVEN REPLACEMENT OF TELEPERM VISUALIZATION WITH PCS

Short description

Refurbishment of process control engineering in waste-to-energy plant Bremerhaven. The existing Teleperm control system was replaced with a PCS7 7.0 SP1.

The following automation stations were installed for this

  • 5 pcs 417-4FH
  • 3 pcs 417-4H
  • 4 pcs 414-3H
  • The following operating stations have been installed or converted.
  • 3 pcs redundant server pairs
  • 7 pcs Operating stations with 1, 2 and 4 monitors
  • The process object volume is: 6034 objects

Contract total

€ 4,500,000

Customer

Bremerhavener Entsorgungsgesellschaft (mbH)
Waste-to-energy plant Bremerhaven
Zur Hexenbrücke 16
27570 Bremerhaven