LANGEN WATERWORKS REFURBISHMENT OF SWITCHGEAR AND CONTROL CABINET PURE WATER PUMPS 3 AND 4

Short description

Refurbishment of cabinet and control cabinet pure water pumps 3 and 4

Planning, construction and production of the low-voltage switchgear and control system

Production of the required LV switchgear and control system.

Preparation of control programs taking into account the RW pump operation on frequency converters.

Connection, commissioning and functional test of the system

Contract total

€ 135,000