TREATMENT PLANT STEINHOF CONVERSION OF VENTILATION SEEPAGE SEWAGE PLANT

Short description

Construction, control engineering, visualization engineering

Conversion of the existing low-voltage main distribution during operation

Fabrication of cable routes and cabling of blowers

Installation of measuring technology, programming of the PCS7 system and commissioning.

All works were carried out during the operation of the sewage treatment plant.

Contract total

€ 69,000

Customer

Abwasserverband Braunschweig (wastewater association)